Solar, wind and battery projects near Heriot (EH38)
19 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of EH38 (Scottish Borders): 3 are waiting for a planning decision, 2 approved but not yet running, 7 operational. The largest live scheme is Penicuik, Moorfoot Hills - Torfichen Wind Farm (108 MW wind farm, application submitted on 28 November 2023, no decision recorded; REPD status may be out of date), 6.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of EH38
Projects of 1 MW and more (18)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Falahillwind farm | wind farm | 6.7 | refusedupdated May 2006 | Dec 2004 | refused May 2006 | May 2006 | Scottish Borders | 1.7 |
| Wull Muir Wind Farmwind farm | wind farm | 36 | refusedupdated Aug 2024 | Dec 2022 | refused Jul 2024 | Aug 2024 | Scottish Borders | 1.7 |
| Carcant Windfarmwind farm | wind farm | 6 | operationalupdated Jan 2015 | Oct 2005 | granted Sep 2006 | Jan 2015 | Scottish Borders | 4.3 |
| Toddleburnwind farm | wind farm | 27.6 | operationalupdated Oct 2010 | Sep 2004 | granted Aug 2005 | Oct 2010 | Scottish Borders | 4.8 |
| Gilston Hill Wind Farmwind farm | wind farm | 21 | refused on appealupdated Apr 2020 | Feb 2017 | refused Feb 2017 | Apr 2020 | Midlothian | 4.9 |
| Wind Farm at Greystone Knowe Wind Farmwind farm | wind farm | 75 | application submitted may be out of dateupdated Nov 2021 | Oct 2021 | — | Nov 2021 | Scottish Borders | 5.0 |
| Gilston Wind Farm (Lothian)wind farm | wind farm | 18.5 | refused on appealupdated Sep 2013 | Dec 2011 | refused Dec 2012 | Sep 2013 | Midlothian | 6.4 |
| Gilston Wind Farm (Borders)wind farm | wind farm | 14.4 | refused on appealupdated Sep 2013 | Dec 2011 | refused Dec 2012 | Sep 2013 | Midlothian | 6.4 |
| Penicuik, Moorfoot Hills - Torfichen Wind Farmwind farm | wind farm | 108 | application submitted may be out of dateupdated Feb 2023 | Nov 2023 | — | Feb 2023 | Midlothian | 6.5 |
| Penicuik, Moorfoot Hills - Torfichen Wind Farmbattery storage | battery storage | 50 | application submitted may be out of dateupdated Mar 2023 | Nov 2023 | — | Mar 2023 | Midlothian | 6.5 |
| Dun Law Extensionwind farm | wind farm | 29.8 | operationalupdated Sep 2013 | Apr 2005 | granted Jan 2006 | Sep 2013 | Scottish Borders | 7.0 |
| Dun Lawwind farm | wind farm | 17.2 | operationalupdated Sep 2013 | May 1996 | granted Jul 1997 | Sep 2013 | Midlothian | 7.4 |
| Rowantree Wind Farmwind farm | wind farm | 69 | refusedupdated May 2014 | Dec 2009 | refused May 2014 | May 2014 | Scottish Borders | 7.9 |
| Pogbie Wind Farm 1wind farm | wind farm | 5.1 | operationalupdated Apr 2019 | Sep 2008 | granted Sep 2009 | Apr 2019 | East Lothian | 9.0 |
| Keith Hillwind farm | wind farm | 4.5 | operationalupdated Sep 2018 | Nov 2010 | granted Apr 2011 | Sep 2018 | East Lothian | 9.1 |
| Ditcher Law Wind Farmwind farm | wind farm | 52.8 | approved, not builtupdated Jun 2026 | Aug 2023 | granted Feb 2026 | Jun 2026 | Scottish Borders | 9.5 |
| Ditcher Law Wind Farmbattery storage | battery storage | 30 | approved, not builtupdated Jun 2026 | Aug 2023 | granted Feb 2026 | Jun 2026 | Scottish Borders | 9.5 |
| Pogbie Wind Farm 2wind farm | wind farm | 4.8 | operationalupdated Dec 2019 | Aug 2015 | granted May 2016 | Dec 2019 | East Lothian | 9.8 |
Smaller schemes under 1 MW, mostly rooftop solar (1)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Wull Muir Wind Farmbattery storage | battery storage | — | refusedupdated Aug 2024 | Dec 2022 | refused Jul 2024 | Aug 2024 | Scottish Borders | 2.5 |
Distance from the average position of the EH38 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Wind farm | 16 | 2 | 1 | 7 | 6 | 236 |
| Battery storage | 3 | 1 | 1 | 0 | 1 | 80 |
MW in pipeline: pending, approved and under-construction capacity.
How Scottish Borders decides solar, wind and battery applications
| Applications | Scottish Borders | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 61 | 10,236 |
| Refused | 28 (46%) | 19% |
| Solar refused | 0 of 13 | 12% |
| Onshore wind refused | 26 of 43 | 45% |
| Battery storage refused | 2 of 5 | 16% |
| Median time from submission to decision | 51.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 11 / 6 | — |
All projects in Scottish Borders
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near EH38, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.