Toddleburn (27.6 MW wind farm)
Toddleburn is a 27.6 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 12 October 2010; the record was last updated on 28 October 2010.
27.6 MWwind farm
operationalstatus in REPD
28 October 2010record last updated
Scottish Borderscouncil area
Planning timeline
| Date | Stage |
|---|---|
| 2 September 2004 | Application submitted |
| 31 August 2005 | Planning permission granted |
| 1 April 2010 | Construction started |
| 12 October 2010 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 27.6 MW
- Status (REPD)
- operational
- Record last updated
- 28 October 2010
- Operator or applicant
- Scottish and Southern Energy (SSE)
- Planning authority
- Scottish Borders
- Planning application reference
- 04/017744/FUL
- Turbines
- 12
- Address (REPD)
- Oxton
- Council area (by location)
- Scottish Borders
- Time to decision
- 52 weeks
- REPD reference
- 3457
Who decides
| Applications | Scottish Borders | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 61 | 10,236 |
| Refused | 28 (46%) | 19% |
| Solar refused | 0 of 13 | 12% |
| Onshore wind refused | 26 of 43 | 45% |
| Battery storage refused | 2 of 5 | 16% |
| Median time from submission to decision | 51.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 11 / 6 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Dun Law Extension | wind farm | 29.8 | operational | 3.0 |
| Rowantree Wind Farm | wind farm | 69 | refused | 3.7 |
| Gilston Hill Wind Farm | wind farm | 21 | refused on appeal | 4.3 |
| Dun Law | wind farm | 17.2 | operational | 4.6 |
| Ditcher Law Wind Farm | wind farm | 52.8 | approved, not built | 5.4 |
| Wull Muir Wind Farm | wind farm | 36 | refused | 5.7 |
| Falahill | wind farm | 6.7 | refused | 6.3 |
| Gilston Wind Farm (Borders) | wind farm | 14.4 | refused on appeal | 6.4 |
| Gilston Wind Farm (Lothian) | wind farm | 18.5 | refused on appeal | 6.4 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7686, -2.8774).