Energy Projects Near You

Toddleburn (27.6 MW wind farm)

Toddleburn is a 27.6 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 12 October 2010; the record was last updated on 28 October 2010.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

27.6 MWwind farm
operationalstatus in REPD
28 October 2010record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
2 September 2004Application submitted
31 August 2005Planning permission granted
1 April 2010Construction started
12 October 2010Operational

Project details

Technology
wind farm
Capacity
27.6 MW
Status (REPD)
operational
Record last updated
28 October 2010
Operator or applicant
Scottish and Southern Energy (SSE)
Planning authority
Scottish Borders
Planning application reference
04/017744/FUL
Turbines
12
Address (REPD)
Oxton
Council area (by location)
Scottish Borders
Time to decision
52 weeks
REPD reference
3457

Who decides

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Dun Law Extensionwind farm29.8operational3.0
Rowantree Wind Farmwind farm69refused3.7
Gilston Hill Wind Farmwind farm21refused on appeal4.3
Dun Lawwind farm17.2operational4.6
Ditcher Law Wind Farmwind farm52.8approved, not built5.4
Wull Muir Wind Farmwind farm36refused5.7
Falahillwind farm6.7refused6.3
Gilston Wind Farm (Borders)wind farm14.4refused on appeal6.4
Gilston Wind Farm (Lothian)wind farm18.5refused on appeal6.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7686, -2.8774).