Energy Projects Near You

Ditcher Law Wind Farm (52.8 MW)

Ditcher Law Wind Farm is a 52.8 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 13 February 2026, not yet built; the record was last updated on 22 June 2026. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

52.8 MWwind farm
approved, not builtstatus in REPD
22 June 2026record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
8 August 2023Application submitted
13 February 2026Section 36 consent granted (Scottish Ministers)
13 February 2031Permission due to expire (unless work starts)

Project details

Technology
wind farm
Capacity
52.8 MW
Status (REPD)
approved, not built
Record last updated
22 June 2026
Operator or applicant
E Power Ltd
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004890
Turbines
8
Turbine height
200 m
Address (REPD)
N/S/E & W/O Vineleaf Cottage
Council area (by location)
Scottish Borders
Time to decision
131 weeks
REPD reference
8376

The scheme also includes 30 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Dun Law Extensionwind farm29.8operational2.6
Dun Lawwind farm17.2operational2.9
Pogbie Wind Farm 1wind farm5.1operational3.5
Longcroft Wind Farmwind farm125application submitted4.7
Toddleburnwind farm27.6operational5.4
Gilston Hill Wind Farmwind farm21refused on appeal5.7
Rowantree Wind Farmwind farm69refused6.6
Gilston Wind Farm (Lothian)wind farm18.5refused on appeal6.6
Gilston Wind Farm (Borders)wind farm14.4refused on appeal6.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7948, -2.804).