Pogbie Wind Farm 1 (5.1 MW)

Pogbie Wind Farm 1 is a 5.1 MW wind farm project in East Lothian, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 29 March 2019; the record was last updated on 2 April 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.1 MWwind farm
operationalstatus in REPD
2 April 2019record last updated
East Lothiancouncil area

Planning timeline

DateStage
1 September 2008Application submitted
2 September 2009Planning permission granted
1 November 2016Construction started
29 March 2019Operational

Project details

Technology
wind farm
Capacity
5.1 MW
Status (REPD)
operational
Record last updated
2 April 2019
Operator or applicant
Mongoose (formerly Energy Law Unlimited)
Planning authority
East Lothian
Planning application reference
08/00823/FUL
Turbines
6
Address (REPD)
Humbie, East Lammermuirs, East Lothian.EH36 5PN
Council area (by location)
East Lothian
Time to decision
52 weeks
REPD reference
4434

Who decides

ApplicationsEast LothianUK
Decided applications (solar, wind, battery)1510,236
Refused1 (7%)19%
Solar refused0 of 612%
Onshore wind refused1 of 745%
Battery storage refused0 of 216%
Median time from submission to decision34.3 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Dun Lawwind farm17.2operational1.9
Ditcher Law Wind Farmwind farm52.8approved, not built3.5
Gilston Wind Farm (Lothian)wind farm18.5refused on appeal3.9
Gilston Wind Farm (Borders)wind farm14.4refused on appeal3.9
Dun Law Extensionwind farm29.8operational3.9
Gilston Hill Wind Farmwind farm21refused on appeal4.1
Toddleburnwind farm27.6operational6.5
Longcroft Wind Farmwind farm125application submitted7.2
Rowantree Wind Farmwind farm69refused9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8218, -2.833).