Energy Projects Near You

Longcroft Wind Farm (125 MW)

Longcroft Wind Farm is a 125 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 31 October 2023, no decision recorded; the record was last updated on 17 November 2023. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

125 MWwind farm
application submittedmay be out of datestatus in REPD
17 November 2023record last updated
Scottish Borderscouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
31 October 2023Application submitted

Project details

Technology
wind farm
Capacity
125 MW
Status (REPD)
application submitted
Record last updated
17 November 2023
Operator or applicant
Renewable Energy Systems
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004774
Turbines
19
Turbine height
220 m
Address (REPD)
Longcroft Wind Farm Land East Of Longcroft Farmhouse Oxton
Council area (by location)
Scottish Borders
REPD reference
13538

The scheme also includes 50 MW of battery storage, recorded separately in REPD (application submitted).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Ditcher Law Wind Farmwind farm52.8approved, not built4.7
Fallago Rigwind farm144operational4.8
Keepers House, Byrecleughbattery storage49.5approved, not built5.1
Dun Law Extensionwind farm29.8operational7.2
Pogbie Wind Farm 1wind farm5.1operational7.2
Brunta Hill Wind Farmwind farm18.4refused on appeal7.4
Dun Lawwind farm17.2operational7.5
Rowantree Wind Farmwind farm69refused9.5
Girthgate Wind Farmwind farm81.6appeal withdrawn9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7945, -2.7287).