Brunta Hill Wind Farm (18.4 MW)

Brunta Hill Wind Farm is an 18.4 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 19 June 2014; the record was last updated on 23 June 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18.4 MWwind farm
refused on appealstatus in REPD
23 June 2014record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
20 October 2011Application submitted
5 August 2013Refused by the planning authority
19 June 2014Appeal refused

Project details

Technology
wind farm
Capacity
18.4 MW
Status (REPD)
refused on appeal
Record last updated
23 June 2014
Operator or applicant
PNE Wind UK Ltd (Brookfield)
Planning authority
Scottish Borders
Planning application reference
11/01444/FUL
Appeal reference
13/00044/REF
Turbines
8
Address (REPD)
Land North East Of Blythe Farm (Brunta Hill), Lauder, Scottish Borders
Council area (by location)
Scottish Borders
Time to decision
94 weeks
REPD reference
4077

Who decides

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Dunside Wind Farmwind farm108approved, not built7.3
Longcroft Wind Farmwind farm125application submitted7.4
Keepers House, Byrecleughbattery storage49.5approved, not built7.4
Corsbie Moor Wind Farmwind farm27refused on appeal7.6
Fallago Rigwind farm144operational8.8
Fallago Rig 2 (extension)wind farm41refused on appeal10.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7602, -2.6271).