Energy Projects Near You

Fallago Rig 2 (extension) (41 MW wind farm)

Fallago Rig 2 (extension) is a 41 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 25 June 2020; the record was last updated on 9 July 2020. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

41 MWwind farm
refused on appealstatus in REPD
9 July 2020record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
29 January 2016Application submitted
21 December 2016Appeal lodged
25 June 2020Refused by the planning authority
25 June 2020Appeal refused

Project details

Technology
wind farm
Capacity
41 MW
Status (REPD)
refused on appeal
Record last updated
9 July 2020
Operator or applicant
EDF Energy Renewables
Planning authority
Scottish Government (S36)
Planning application reference
EC00003102
Appeal reference
WIN-140-5
Turbines
12
Turbine height
127 m
Address (REPD)
Fallago Rig 2, Longformacus, Duns
Council area (by location)
Scottish Borders
Time to decision
230 weeks
REPD reference
4964

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Lees Hill Energy Parksolar farm60application submitted2.1
Lees Hill Energy Parkwind farm36application submitted2.1
Black Hill (Borders)wind farm28.6operational3.9
Inch Moor Wind Farmwind farm51.2application withdrawn4.3
Dunside Wind Farmwind farm108approved, not built4.5
Crystal Rig Phase 1 Repoweringwind farm72application submitted8.4
Crystal Rig Phase 1wind farm62.5operational8.4
Lees Hill Energy Parkbattery storage60application submitted9.8
Aikengall IIa Community Wind Farmwind farm81.7operational9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.808, -2.4924).