Aikengall IIa Community Wind Farm (81.7 MW)

Aikengall IIa Community Wind Farm is an 81.7 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 November 2021; the record was last updated on 27 September 2021. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

81.7 MWwind farm
operationalstatus in REPD
27 September 2021record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
1 February 2014Application submitted
23 April 2015Appeal lodged
19 October 2016Section 36 consent granted (Scottish Ministers)
19 October 2016Appeal allowed
1 January 2021Construction started
1 November 2021Operational

Project details

Technology
wind farm
Capacity
81.7 MW
Status (REPD)
operational
Record last updated
27 September 2021
Operator or applicant
Community Windpower
Planning authority
Scottish Government (S36)
Planning application reference
not recorded
Appeal reference
WIN-140-3
Turbines
19
Turbine height
145 m
Address (REPD)
Land North Of Nether Monynut Cottage Cockburnspath Scottish Borders
Council area (by location)
Scottish Borders
Time to decision
142 weeks
REPD reference
4591

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Ferneylea Farmwind farm18application withdrawn2.2
Aikengall II Community Wind Farm Batterybattery storage80operational2.6
Aikengall II, Wester Dod Community Wind Farmwind farm60.8operational3.5
Aikengallwind farm48operational3.5
Crystal Rig Phase 1 Repoweringwind farm72application submitted3.6
Crystal Rig Phase 1wind farm62.5operational3.6
Crystal Rig Wind Farm Phase IVwind farm48under construction4.8
Crystal Rig Wind Farm Phase 2awind farm138operational4.8
Hoprigshiels Community Wind Farmwind farm6.9operational4.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8934, -2.4526).