Aikengall II Community Wind Farm Battery (80 MW)

Aikengall II Community Wind Farm Battery is an 80 MW battery storage project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 June 2021; the record was last updated on 27 March 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

80 MWbattery storage
operationalstatus in REPD
27 March 2023record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
10 January 2018Application submitted
25 January 2019Planning permission granted
1 December 2020Construction started
1 June 2021Operational

Project details

Technology
battery storage (co-located with re)
Capacity
80 MW
Status (REPD)
operational
Record last updated
27 March 2023
Operator or applicant
Community Wind Power
Planning authority
Scottish Borders
Planning application reference
18/00865/P
Address (REPD)
Aikengall II Community Wind Fa, Innerwick, Dunbar, Lothian
Council area (by location)
Scottish Borders
Time to decision
54 weeks
REPD reference
7015

Recorded together with Aikengall II, Wester Dod Community Wind Farm (60.8 MW wind farm, operational).

Who decides

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Aikengallwind farm48operational1.1
Aikengall IIa Community Wind Farmwind farm81.7operational2.6
Crystal Rig Wind Farm Phase IVwind farm48under construction2.7
Crystal Rig Wind Farm Phase 2awind farm138operational2.9
Crystal Rig Phase 1 Repoweringwind farm72application submitted3.1
Crystal Rig Phase 1wind farm62.5operational3.1
Ferneylea Farmwind farm18application withdrawn3.5
Crystal Rig Wind Farm Phase IIIwind farm13.8operational3.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.9076, -2.4856).