Energy Projects Near You

Crystal Rig Wind Farm Phase IV (48 MW)

Crystal Rig Wind Farm Phase IV is a 48 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 August 2024; the record was last updated on 3 February 2024. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

48 MWwind farm
under constructionstatus in REPD
3 February 2024record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
30 May 2018Application submitted
4 July 2019Appeal lodged
24 March 2021Section 36 consent granted (Scottish Ministers)
24 March 2021Appeal allowed
1 August 2024Construction started

Project details

Technology
wind farm
Capacity
48 MW
Status (REPD)
under construction
Record last updated
3 February 2024
Operator or applicant
Fred Olsen Renewables
Planning authority
Scottish Government (S36)
Planning application reference
ECU00000607
Appeal reference
WIN-140-8
Turbines
11
Turbine height
200 m
Address (REPD)
Crystal Rigg Wind Farm Cranshaws Duns Scottish Borders
Council area (by location)
Scottish Borders
Time to decision
147 weeks
Contracts for Difference
AR6
REPD reference
4631

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Crystal Rig Wind Farm Phase 2awind farm138operational0.4
Crystal Rig Extension IIwind farm20.7operational1.6
Crystal Rig Solar Farmsolar farm27.5approved, not built2.4
Crystal Rig Phase 1wind farm62.5operational2.6
Crystal Rig Phase 1 Repoweringwind farm72application submitted2.6
Crystal Rig Wind Farm Phase IIIwind farm13.8operational2.6
Aikengall II Community Wind Farm Batterybattery storage80operational2.7
Aikengallwind farm48operational2.8
Aikengall II, Wester Dod Community Wind Farmwind farm60.8operational2.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.9031, -2.5278).