Energy Projects Near You

Crystal Rig Extension II (20.7 MW wind farm)

Crystal Rig Extension II is a 20.7 MW wind farm project in East Lothian, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 25 October 2010; the record was last updated on 8 October 2013. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20.7 MWwind farm
operationalstatus in REPD
8 October 2013record last updated
East Lothiancouncil area

Planning timeline

DateStage
1 May 2004Application submitted
25 May 2005Section 36 consent granted (Scottish Ministers)
1 August 2008Construction started
25 October 2010Operational

Project details

Technology
wind farm
Capacity
20.7 MW
Status (REPD)
operational
Record last updated
8 October 2013
Operator or applicant
Natural Power Consultants
Planning authority
Scottish Government (S36)
Planning application reference
not recorded
Turbines
9
Address (REPD)
Lammermuir Hills on the East Lothian Council/Scottish Borders Council border approximately 11km from Dunbar and 16.5km from Duns.
Council area (by location)
East Lothian
Time to decision
56 weeks
REPD reference
3536

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Crystal Rig Wind Farm Phase IVwind farm48under construction1.6
Crystal Rig Wind Farm Phase IIIwind farm13.8operational1.7
Crystal Rig Wind Farm Phase 2awind farm138operational1.8
Crystal Rig Solar Farmsolar farm27.5approved, not built2.4
Aikengall II, Wester Dod Community Wind Farmwind farm60.8operational3.5
Aikengallwind farm48operational3.5
Aikengall II Community Wind Farm Batterybattery storage80operational3.8
Crystal Rig Phase 1 Repoweringwind farm72application submitted4.1
Crystal Rig Phase 1wind farm62.5operational4.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.9129, -2.5455).