Energy Projects Near You

Crystal Rig Wind Farm Phase III (13.8 MW)

Crystal Rig Wind Farm Phase III is a 13.8 MW wind farm project in East Lothian, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 22 December 2016; the record was last updated on 1 June 2018. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13.8 MWwind farm
operationalstatus in REPD
1 June 2018record last updated
East Lothiancouncil area

Planning timeline

DateStage
14 June 2013Application submitted
18 June 2015Section 36 consent granted (Scottish Ministers)
15 January 2016Construction started
22 December 2016Operational

Project details

Technology
wind farm
Capacity
13.8 MW
Status (REPD)
operational
Record last updated
1 June 2018
Operator or applicant
Fred Olsen Renewables
Planning authority
Scottish Government (S36)
Planning application reference
not recorded
Turbines
6
Address (REPD)
Crystal Rigg Wind Farm, Cranshaws Duns, Scottish Borders
Council area (by location)
East Lothian
Time to decision
105 weeks
REPD reference
4215

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Crystal Rig Extension IIwind farm20.7operational1.7
Crystal Rig Wind Farm Phase IVwind farm48under construction2.6
Aikengallwind farm48operational3.0
Aikengall II, Wester Dod Community Wind Farmwind farm60.8operational3.0
Crystal Rig Wind Farm Phase 2awind farm138operational3.0
Aikengall II Community Wind Farm Batterybattery storage80operational3.7
Crystal Rig Solar Farmsolar farm27.5approved, not built4.0
Aikengall, Innerwickbattery storage19.9approved, not built4.9
Crystal Rig Phase 1wind farm62.5operational5.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.9264, -2.5345).