Energy Projects Near You

Crystal Rig Wind Farm Phase 2a (138 MW)

Crystal Rig Wind Farm Phase 2a is a 138 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 25 October 2010; the record was last updated on 28 October 2010. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

138 MWwind farm
operationalstatus in REPD
28 October 2010record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
17 July 2007Application submitted
30 July 2008Section 36 consent granted (Scottish Ministers)
1 March 2010Construction started
25 October 2010Operational

Project details

Technology
wind farm
Capacity
138 MW
Status (REPD)
operational
Record last updated
28 October 2010
Operator or applicant
Fred Olsen Renewables
Planning authority
Scottish Government (S36)
Planning application reference
not recorded
Turbines
60
Address (REPD)
Dundfar Common, Eastern Lammermuirs
Council area (by location)
Scottish Borders
Time to decision
54 weeks
REPD reference
3440

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Crystal Rig Wind Farm Phase IVwind farm48under construction0.4
Crystal Rig Extension IIwind farm20.7operational1.8
Crystal Rig Solar Farmsolar farm27.5approved, not built2.1
Crystal Rig Phase 1wind farm62.5operational2.3
Crystal Rig Phase 1 Repoweringwind farm72application submitted2.3
Aikengall II Community Wind Farm Batterybattery storage80operational2.9
Crystal Rig Wind Farm Phase IIIwind farm13.8operational3.0
Aikengall II, Wester Dod Community Wind Farmwind farm60.8operational3.1
Aikengallwind farm48operational3.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8995, -2.5293).