Energy Projects Near You

Renewable energy projects in East Lothian

32 solar, wind or battery projects of 150 kW or more are located in East Lothian (REPD, July 2026 extract): 5 pending, 15 approved but not running, 9 operational and 0 refused. The council refused 1 of 15 decided applications (7%; UK 19%), with a median 34 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

32projects in the council area
5awaiting a decision
15approved, not running
7%of decisions refused

How East Lothian decides

ApplicationsEast LothianUK
Decided applications (solar, wind, battery)1510,236
Refused1 (7%)19%
Solar refused0 of 612%
Onshore wind refused1 of 745%
Battery storage refused0 of 216%
Median time from submission to decision34.3 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Projects in East Lothian

Projects of 1 MW and more (23)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Braxbess Battery Storagebattery storagebattery storage650approved, not builtupdated Oct 2025Nov 2023granted Jul 2025Oct 2025
Cockenzie Battery Storage System - Site Abattery storagebattery storage240approved, not builtupdated Oct 2025Aug 2023granted Jul 2025Oct 2025
Smeaton Battery Energy Storage Systembattery storagebattery storage228approved, not builtupdated Oct 2024Mar 2023granted Aug 2024Oct 2024
Springfield Solar Farm & Battery Energy Storagesolar farmsolar farm165application submittedupdated Oct 2025Jun 2025—Oct 2025
Newlands Hill Wind Energy Hubwind farmwind farm136application submitted may be out of dateupdated Dec 2023Nov 2023—Dec 2023
Newlands Hill Wind Energy Hubbattery storagebattery storage136application submitted may be out of dateupdated Dec 2023Nov 2023—Dec 2023
Cockenzie Battery Storage System - Site Bbattery storagebattery storage102approved, not builtupdated Oct 2025Nov 2024granted Jul 2025Oct 2025
Springfield Solar Farm & Battery Energy Storagebattery storagebattery storage80application submittedupdated Oct 2025Jun 2025—Oct 2025
Dolphingstone Farmbattery storagebattery storage63approved, not builtupdated Oct 2025Nov 2023granted Jul 2025Oct 2025
Aikengall II, Wester Dod Community Wind Farmwind farmwind farm60.8operationalupdated Oct 2021Sep 2009granted Mar 2013Oct 2021
Dunbar Grid Substationbattery storagebattery storage49.9approved, not builtupdated Oct 2024Jan 2024granted Oct 2024Oct 2024
Aikengallwind farmwind farm48operationalupdated Sep 2014Feb 2005granted Mar 2007Sep 2014
Crystal Rig Solar Farmsolar farmsolar farm27.5approved, not builtupdated Oct 2025Jul 2024granted Jul 2025Oct 2025
Crystal Rig Extension IIwind farmwind farm20.7operationalupdated Oct 2013May 2004granted May 2005Oct 2013
Aikengall, Innerwickbattery storagebattery storage19.9approved, not builtupdated Sep 2024Oct 2023granted Aug 2024Sep 2024
Ferneylea Farmwind farmwind farm18application withdrawnupdated Oct 2018Jul 2015—Oct 2018
Crystal Rig Wind Farm Phase IIIwind farmwind farm13.8operationalupdated Jun 2018Jun 2013granted Jun 2015Jun 2018
Townhead Farmwind farmwind farm6application withdrawnupdated Sep 2014May 2009—Sep 2014
Pogbie Wind Farm 1wind farmwind farm5.1operationalupdated Apr 2019Sep 2008granted Sep 2009Apr 2019
Pogbie Wind Farm 2wind farmwind farm4.8operationalupdated Dec 2019Aug 2015granted May 2016Dec 2019
Keith Hillwind farmwind farm4.5operationalupdated Sep 2018Nov 2010granted Apr 2011Sep 2018
Dunbar Energy Parksolar farmsolar farm2permission expiredupdated Feb 2018Oct 2011granted Mar 2012Feb 2018
Ferneylea Farmwind farmwind farm1.5operationalupdated May 2017Sep 2010granted Mar 2012May 2017
Smaller schemes under 1 MW, mostly rooftop solar (9)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Howden Farm Turbine, Giffordwind turbinewind turbine0.9approved, not builtupdated May 2026Oct 2024granted Sep 2025May 2026
Dunbar Waste Water Treatment Works, Beltonford Hedderwicksolar farmsolar farm0.3approved, not built may be out of dateupdated Feb 2023Nov 2022granted Jan 2023Feb 2023
Meadow Stores, Ormistonsolar farmsolar farm0.2approved, not builtupdated Nov 2024Sep 2024granted Nov 2024Nov 2024
Haddington Sewage Works, Haddington Eastrooftop solarrooftop solar0.2application submittedupdated May 2026Apr 2026—May 2026
Howden Farmrooftop solarrooftop solar0.2operationalupdated Sep 2023Mar 2020granted Apr 2020Sep 2023
Seton Sands, Holiday Villagerooftop solarrooftop solar0.2approved, not built may be out of dateupdated Jul 2023May 2023granted Jun 2023Jul 2023
Smeaton Nursery Garden, Smeatonsolar farmsolar farm0.1approved, not builtupdated Dec 2025Feb 2025granted Apr 2025Dec 2025
Thorntonloch, Innerwick - Branxton Energy Storage Facilitybattery storagebattery storage—approved, not builtupdated Jan 2024Nov 2022granted Dec 2023Jan 2024
Ruchlaw Mains, Stentonwind turbinewind turbine—approved, not builtupdated Sep 2024Jun 2024granted Aug 2024Sep 2024

Postcode districts in East Lothian

DistrictProjects within 10 kmPendingApprovedOperational
EH21183141
EH312110
EH326060
EH337070
EH3412072
EH35140111
EH3614047
EH392110
EH408340
EH415121
EH4215275

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to East Lothian by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.