Solar, wind and battery projects near East Linton (EH40)
8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of EH40 (East Lothian): 3 are waiting for a planning decision, 4 approved but not yet running. The largest live scheme is Springfield Solar Farm & Battery Energy Storage (165 MW solar farm, application submitted on 6 June 2025, no decision recorded), 6.8 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Levenmouth demonstration turbine (Fife Energy Park) (7 MW, operational), 26.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of EH40
Projects of 1 MW and more (4)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Dunbar Grid Substationbattery storage | battery storage | 49.9 | approved, not builtupdated Oct 2024 | Jan 2024 | granted Oct 2024 | Oct 2024 | East Lothian | 5.7 |
| Springfield Solar Farm & Battery Energy Storagesolar farm | solar farm | 165 | application submittedupdated Oct 2025 | Jun 2025 | — | Oct 2025 | East Lothian | 6.8 |
| Springfield Solar Farm & Battery Energy Storagebattery storage | battery storage | 80 | application submittedupdated Oct 2025 | Jun 2025 | — | Oct 2025 | East Lothian | 6.8 |
| Dunbar Energy Parksolar farm | solar farm | 2 | permission expiredupdated Feb 2018 | Oct 2011 | granted Mar 2012 | Feb 2018 | East Lothian | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (4)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Smeaton Nursery Garden, Smeatonsolar farm | solar farm | 0.1 | approved, not builtupdated Dec 2025 | Feb 2025 | granted Apr 2025 | Dec 2025 | East Lothian | 1.8 |
| Ruchlaw Mains, Stentonwind turbine | wind turbine | — | approved, not builtupdated Sep 2024 | Jun 2024 | granted Aug 2024 | Sep 2024 | East Lothian | 4.1 |
| Dunbar Waste Water Treatment Works, Beltonford Hedderwicksolar farm | solar farm | 0.3 | approved, not built may be out of dateupdated Feb 2023 | Nov 2022 | granted Jan 2023 | Feb 2023 | East Lothian | 5.8 |
| Haddington Sewage Works, Haddington Eastrooftop solar | rooftop solar | 0.2 | application submittedupdated May 2026 | Apr 2026 | — | May 2026 | East Lothian | 6.2 |
Distance from the average position of the EH40 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 4 | 1 | 2 | 0 | 0 | 165 |
| Rooftop solar | 1 | 1 | 0 | 0 | 0 | 0.2 |
| Wind turbine | 1 | 0 | 1 | 0 | 0 | 0 |
| Battery storage | 2 | 1 | 1 | 0 | 0 | 130 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Levenmouth demonstration turbine (Fife Energy Park) | 7 | operationalupdated Nov 2018 | 26.5 |
| Forthwind | 20 | approved, not builtupdated Aug 2023 | 27.8 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How East Lothian decides solar, wind and battery applications
| Applications | East Lothian | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 15 | 10,236 |
| Refused | 1 (7%) | 19% |
| Solar refused | 0 of 6 | 12% |
| Onshore wind refused | 1 of 7 | 45% |
| Battery storage refused | 0 of 2 | 16% |
| Median time from submission to decision | 34.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 1 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near EH40, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.