Energy Projects Near You

Solar, wind and battery projects near Haddington (EH41)

5 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of EH41 (East Lothian): 1 is waiting for a planning decision, 2 approved but not yet running, 1 operational. The largest live scheme is Howden Farm Turbine, Gifford (0.9 MW wind turbine, approved on 3 September 2025, not yet built), 5.8 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Levenmouth demonstration turbine (Fife Energy Park) (7 MW, operational), 26.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5projects within 10 km
1awaiting a decision
2approved, not running
1operational

Projects within 10 km of EH41

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Townhead Farmwind farmwind farm6application withdrawnupdated Sep 2014May 2009—Sep 2014East Lothian5.9
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Haddington Sewage Works, Haddington Eastrooftop solarrooftop solar0.2application submittedupdated May 2026Apr 2026—May 2026East Lothian2.5
Howden Farm Turbine, Giffordwind turbinewind turbine0.9approved, not builtupdated May 2026Oct 2024granted Sep 2025May 2026East Lothian5.8
Howden Farmrooftop solarrooftop solar0.2operationalupdated Sep 2023Mar 2020granted Apr 2020Sep 2023East Lothian6.2
Seton Sands, Holiday Villagerooftop solarrooftop solar0.2approved, not built may be out of dateupdated Jul 2023May 2023granted Jun 2023Jul 2023East Lothian9.8

Distance from the average position of the EH41 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Rooftop solar311100.4
Wind farm100000
Wind turbine101000.9

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Levenmouth demonstration turbine (Fife Energy Park)7operationalupdated Nov 201826.1
Forthwind20approved, not builtupdated Aug 202326.7

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How East Lothian decides solar, wind and battery applications

ApplicationsEast LothianUK
Decided applications (solar, wind, battery)1510,236
Refused1 (7%)19%
Solar refused0 of 612%
Onshore wind refused1 of 745%
Battery storage refused0 of 216%
Median time from submission to decision34.3 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

All projects in East Lothian

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near EH41, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.