Energy Projects Near You

Townhead Farm (6 MW wind farm)

Townhead Farm is a 6 MW wind farm project in East Lothian, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 17 July 2009; the record was last updated on 25 September 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6 MWwind farm
application withdrawnstatus in REPD
25 September 2014record last updated
East Lothiancouncil area

Planning timeline

DateStage
11 May 2009Application submitted
17 July 2009Application withdrawn

Project details

Technology
wind farm
Capacity
6 MW
Status (REPD)
application withdrawn
Record last updated
25 September 2014
Operator or applicant
Private Developer
Planning authority
East Lothian
Planning application reference
09/00385/FUL
Turbines
3
Address (REPD)
Gifford, Haddington, Lothian. EH41 4PG
Council area (by location)
East Lothian
REPD reference
4443

Who decides

ApplicationsEast LothianUK
Decided applications (solar, wind, battery)1510,236
Refused1 (7%)19%
Solar refused0 of 612%
Onshore wind refused1 of 745%
Battery storage refused0 of 216%
Median time from submission to decision34.3 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Newlands Hill Wind Energy Hubwind farm136application submitted6.2
Fallago Rigwind farm144operational8.6
Keepers House, Byrecleughbattery storage49.5approved, not built9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.9061, -2.7212).