Newlands Hill Wind Energy Hub (136 MW)

Newlands Hill Wind Energy Hub is a 136 MW wind farm project in East Lothian, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 14 November 2023, no decision recorded; the record was last updated on 7 December 2023. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

136 MWwind farm
application submittedmay be out of datestatus in REPD
7 December 2023record last updated
East Lothiancouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
14 November 2023Application submitted

Project details

Technology
wind farm
Capacity
136 MW
Status (REPD)
application submitted
Record last updated
7 December 2023
Operator or applicant
Belltown Power Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004603
Turbines
17
Turbine height
200 m
Address (REPD)
Lammermuir Hills, Gifford
Council area (by location)
East Lothian
REPD reference
12289

The scheme also includes 136 MW of battery storage, recorded separately in REPD (application submitted).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Crystal Rig Solar Farmsolar farm27.5approved, not built5.3
Fallago Rigwind farm144operational5.6
Keepers House, Byrecleughbattery storage49.5approved, not built5.8
Townhead Farmwind farm6application withdrawn6.2
Crystal Rig Extension IIwind farm20.7operational7.3
Crystal Rig Wind Farm Phase 2awind farm138operational7.5
Crystal Rig Wind Farm Phase IVwind farm48under construction7.7
Dunside Wind Farmwind farm108approved, not built8.1
Crystal Rig Phase 1wind farm62.5operational8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.874, -2.6398).