Energy Projects Near You

Dunside Wind Farm (108 MW)

Dunside Wind Farm is a 108 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 24 March 2026, not yet built; the record was last updated on 31 March 2026. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

108 MWwind farm
approved, not builtstatus in REPD
31 March 2026record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
16 June 2023Application submitted
24 March 2026Section 36 consent granted (Scottish Ministers)
24 March 2029Permission due to expire (unless work starts)

Project details

Technology
wind farm
Capacity
108 MW
Status (REPD)
approved, not built
Record last updated
31 March 2026
Operator or applicant
EDF Energy
Planning authority
Scottish Government (S36)
Planning application reference
ECU00003436
Turbines
15
Turbine height
220 m
Address (REPD)
W/O Dunside Longformacus Duns
Council area (by location)
Scottish Borders
Time to decision
145 weeks
REPD reference
10865

The scheme also includes 20 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Fallago Rig 2 (extension)wind farm41refused on appeal4.5
Keepers House, Byrecleughbattery storage49.5approved, not built6.4
Lees Hill Energy Parksolar farm60application submitted6.5
Lees Hill Energy Parkwind farm36application submitted6.5
Brunta Hill Wind Farmwind farm18.4refused on appeal7.3
Inch Moor Wind Farmwind farm51.2application withdrawn8.0
Fallago Rigwind farm144operational8.0
Newlands Hill Wind Energy Hubwind farm136application submitted8.1
Crystal Rig Phase 1 Repoweringwind farm72application submitted8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8155, -2.5635).