Energy Projects Near You

Lees Hill Energy Park (60 MW, REPD 11864)

Lees Hill Energy Park is a 60 MW solar farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 16 April 2024, no decision recorded; the record was last updated on 11 June 2024. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

60 MWsolar farm
application submittedmay be out of datestatus in REPD
11 June 2024record last updated
Scottish Borderscouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
16 April 2024Application submitted

Project details

Technology
solar farm
Capacity
60 MW
Status (REPD)
application submitted
Record last updated
11 June 2024
Operator or applicant
Fred Olsen Renewables Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004571
Site area
176.3 ha
Address (REPD)
Lees Hill Energy Park, S/O Black Hill Wind Farm, Stobswood Road, Duns
Council area (by location)
Scottish Borders
REPD reference
11864

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Lees Hill Energy Parkwind farm36application submitted<0.1
Fallago Rig 2 (extension)wind farm41refused on appeal2.1
Black Hill (Borders)wind farm28.6operational2.1
Inch Moor Wind Farmwind farm51.2application withdrawn2.6
Dunside Wind Farmwind farm108approved, not built6.5
Lees Hill Energy Parkbattery storage60application submitted7.8
Crystal Rig Phase 1wind farm62.5operational9.9
Crystal Rig Phase 1 Repoweringwind farm72application submitted9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7976, -2.4651).