Energy Projects Near You

Solar, wind and battery projects near Duns (TD11)

10 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TD11 (Scottish Borders): 5 are waiting for a planning decision, 3 operational. The largest live scheme is Lees Hill Energy Park (60 MW battery storage, application submitted on 16 April 2024, no decision recorded; REPD status may be out of date), 2.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10projects within 10 km
5awaiting a decision
0approved, not running
3operational

Projects within 10 km of TD11

Projects of 1 MW and more (10)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Lees Hill Energy Parkbattery storagebattery storage60application submitted may be out of dateupdated Jun 2024Apr 2024—Jun 2024Scottish Borders2.4
Monashee Wind Farmwind farmwind farm15application withdrawnupdated Jul 2013Apr 2012—Jul 2013Scottish Borders7.1
Black Hill (Borders)wind farmwind farm28.6operationalupdated May 2009Jan 2001granted Jul 2001May 2009Scottish Borders7.6
Monashee Farm, Drakemyrewind farmwind farm24application submittedupdated May 2025Apr 2025—May 2025Scottish Borders8.9
Monashee Wind Farmwind farmwind farm24application submittedupdated May 2025Apr 2025—May 2025Scottish Borders8.9
Brockholes Wind Clusterwind farmwind farm2.4operationalupdated Jun 2013Apr 2009granted May 2010Jun 2013Scottish Borders8.9
Quixwood Moorwind farmwind farm29.9operationalupdated Apr 2017Dec 2011granted Apr 2013Apr 2017Scottish Borders9.2
Inch Moor Wind Farmwind farmwind farm51.2application withdrawnupdated Dec 2016Aug 2015—Dec 2016Scottish Borders9.3
Lees Hill Energy Parksolar farmsolar farm60application submitted may be out of dateupdated Jun 2024Apr 2024—Jun 2024Scottish Borders9.6
Lees Hill Energy Parkwind farmwind farm36application submitted may be out of dateupdated Jun 2024Apr 2024—Jun 2024Scottish Borders9.6

Distance from the average position of the TD11 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm1100060
Wind farm8303084
Battery storage1100060

MW in pipeline: pending, approved and under-construction capacity.

How Scottish Borders decides solar, wind and battery applications

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

All projects in Scottish Borders

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TD11, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.