Solar, wind and battery projects near Eyemouth (TD14)

7 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TD14 (Scottish Borders): 3 approved but not yet running, 2 operational. The largest live scheme is Eyemouth Freezers, Toll Bridge Road (1.2 MW rooftop solar, approved on 4 April 2024, not yet built), 1.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7projects within 10 km
0awaiting a decision
3approved, not running
2operational

Projects within 10 km of TD14

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Eyemouth Freezers, Toll Bridge Roadrooftop solarrooftop solar1.2approved, not builtupdated May 2024Feb 2024granted Apr 2024May 2024Scottish Borders1.5
Wind Turbines at Se/O Reston Hill Farmhousewind farmwind farm20refused on appealupdated Aug 2013Oct 2012refused Aug 2013Aug 2013Scottish Borders4.9
Moorhouse Farmwind farmwind farm1operationalupdated Nov 2018Jun 2013granted Sep 2014Nov 2018Scottish Borders8.9
Drone Hillwind farmwind farm28.6operationalupdated Dec 2017Mar 2005granted Nov 2007Dec 2017Scottish Borders9.2
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Ayton Mains Farmhousewind turbinewind turbine0.2application withdrawnupdated Apr 2024Jan 2024—Apr 2024Scottish Borders1.6
Fish Yard Burgons Limited, Harbour Roadrooftop solarrooftop solar0.2approved, not builtupdated Feb 2024Dec 2023granted Jan 2024Feb 2024Scottish Borders2.3
Pressmains, Coldinghamwind turbinewind turbine0.2approved, not builtupdated Sep 2025May 2025granted Sep 2025Sep 2025Scottish Borders5.4

Distance from the average position of the TD14 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Rooftop solar202001.4
Wind farm300210
Wind turbine201000.2

MW in pipeline: pending, approved and under-construction capacity.

How Scottish Borders decides solar, wind and battery applications

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

All projects in Scottish Borders

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.