Energy Projects Near You

Solar, wind and battery projects near Cornhill-on-Tweed (TD12)

7 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TD12 (Scottish Borders): 2 are waiting for a planning decision, 3 approved but not yet running. The largest live scheme is Eccles II Substation (500 MW battery storage, under construction since 1 January 2026), 5.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7projects within 10 km
2awaiting a decision
3approved, not running
0operational

Projects within 10 km of TD12

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Eccles Substation, Ecclesbattery storagebattery storage50under constructionupdated Aug 2024Dec 2022granted Jun 2023Aug 2024Scottish Borders4.5
Bishops Dalbattery storagebattery storage150application submittedupdated Apr 2025Mar 2025—Apr 2025Scottish Borders4.5
Eccles Battery Energy Storage Systembattery storagebattery storage400under constructionupdated May 2025Sep 2022granted Aug 2023May 2025Scottish Borders5.5
Moneylaws Hillwind farmwind farm11.2application withdrawnupdated Jun 2009——Jun 2009Northumberland5.7
Eccles II Substationbattery storagebattery storage500under constructionupdated Mar 2026May 2023granted Dec 2024Mar 2026Scottish Borders5.8
Toft Hill Windfarmwind farmwind farm19refused on appealupdated Dec 2010Nov 2006refused Mar 2008Dec 2010Northumberland6.8
Pittlesheugh Farm Bess, Springwells Farmhousebattery storagebattery storage340application submitted may be out of dateupdated Jun 2024Apr 2024—Jun 2024Scottish Borders9.2

Distance from the average position of the TD12 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm200010
Battery storage523001,440

MW in pipeline: pending, approved and under-construction capacity.

How Scottish Borders decides solar, wind and battery applications

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

All projects in Scottish Borders

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TD12, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.