Energy Projects Near You

Eccles II Substation (500 MW battery storage)

Eccles II Substation is a 500 MW battery storage project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 January 2026; the record was last updated on 30 March 2026. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

500 MWbattery storage
under constructionstatus in REPD
30 March 2026record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
2 May 2023Application submitted
16 December 2024Section 36 consent granted (Scottish Ministers)
1 January 2026Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
500 MW
Status (REPD)
under construction
Record last updated
30 March 2026
Operator or applicant
Matrix Renewables
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004804
Address (REPD)
W/O Eccles Substation, approximately 2.3 km S/O Leitholm
Council area (by location)
Scottish Borders
Time to decision
85 weeks
Name in REPD
Eccles II Substation - Battery Energy Storage System
REPD reference
14058

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Eccles Battery Energy Storage Systembattery storage400under construction0.4
Bishops Dalbattery storage150application submitted1.3
Eccles Substation, Ecclesbattery storage50under construction1.3
Pittlesheugh Farm Bess, Springwells Farmhousebattery storage340application submitted3.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.6721, -2.3263).