Energy Projects Near You

Solar, wind and battery projects near Greenlaw (TD10)

8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TD10 (Scottish Borders): 4 are waiting for a planning decision, 2 approved but not yet running, 1 operational. The largest live scheme is Eccles II Substation (500 MW battery storage, under construction since 1 January 2026), 9.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8projects within 10 km
4awaiting a decision
2approved, not running
1operational

Projects within 10 km of TD10

Projects of 1 MW and more (8)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Pittlesheugh Farm Bess, Springwells Farmhousebattery storagebattery storage340application submitted may be out of dateupdated Jun 2024Apr 2024—Jun 2024Scottish Borders5.6
Inch Moor Wind Farmwind farmwind farm51.2application withdrawnupdated Dec 2016Aug 2015—Dec 2016Scottish Borders7.0
Eccles II Substationbattery storagebattery storage500under constructionupdated Mar 2026May 2023granted Dec 2024Mar 2026Scottish Borders9.0
Eccles Battery Energy Storage Systembattery storagebattery storage400under constructionupdated May 2025Sep 2022granted Aug 2023May 2025Scottish Borders9.3
Lees Hill Energy Parksolar farmsolar farm60application submitted may be out of dateupdated Jun 2024Apr 2024—Jun 2024Scottish Borders9.6
Lees Hill Energy Parkwind farmwind farm36application submitted may be out of dateupdated Jun 2024Apr 2024—Jun 2024Scottish Borders9.6
Lees Hill Energy Parkbattery storagebattery storage60application submitted may be out of dateupdated Jun 2024Apr 2024—Jun 2024Scottish Borders9.8
Black Hill (Borders)wind farmwind farm28.6operationalupdated May 2009Jan 2001granted Jul 2001May 2009Scottish Borders9.8

Distance from the average position of the TD10 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm1100060
Wind farm3101036
Battery storage422001,300

MW in pipeline: pending, approved and under-construction capacity.

How Scottish Borders decides solar, wind and battery applications

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

All projects in Scottish Borders

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TD10, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.