Energy Projects Near You

Solar, wind and battery projects near Kelso (TD5)

3 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TD5 (Scottish Borders): 3 approved but not yet running. The largest live scheme is Plexus Lee, Forbes Way (0.5 MW rooftop solar, approved on 24 August 2022, not yet built; REPD status may be out of date), 0.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

3projects within 10 km
0awaiting a decision
3approved, not running
0operational

Projects within 10 km of TD5

Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Plexus Lee, Forbes Wayrooftop solarrooftop solar0.5approved, not built may be out of dateupdated Jul 2022Jun 2022granted Aug 2022Jul 2022Scottish Borders0.6
Works Kenneth Forbes, Lee Forbes Wayrooftop solarrooftop solar0.5approved, not built may be out of dateupdated Jul 2023Apr 2023granted Jun 2023Jul 2023Scottish Borders0.6
Kelso High School, Angraflat Roadrooftop solarrooftop solar—approved, not built may be out of dateupdated May 2023Apr 2023granted Jun 2023May 2023Scottish Borders2.6

Distance from the average position of the TD5 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Rooftop solar303001

MW in pipeline: pending, approved and under-construction capacity.

How Scottish Borders decides solar, wind and battery applications

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

All projects in Scottish Borders

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TD5, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.