Solar, wind and battery projects near Lauder (TD2)
16 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TD2 (Scottish Borders): 2 are waiting for a planning decision, 3 approved but not yet running, 3 operational. The largest live scheme is Longcroft Wind Farm (125 MW wind farm, application submitted on 31 October 2023, no decision recorded; REPD status may be out of date), 7.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of TD2
Projects of 1 MW and more (15)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Girthgate Wind Farmwind farm | wind farm | 81.6 | appeal withdrawnupdated Jul 2015 | Jun 2013 | — | Jul 2015 | Scottish Borders | 3.5 |
| Muircleugh Farmwind farm | wind farm | 21 | refused on appealupdated Jan 2016 | Oct 2014 | refused Mar 2015 | Jan 2016 | Scottish Borders | 4.3 |
| Rowantree Wind Farmwind farm | wind farm | 69 | refusedupdated May 2014 | Dec 2009 | refused May 2014 | May 2014 | Scottish Borders | 5.8 |
| Sell Moor Windfarmwind farm | wind farm | 47.5 | refusedupdated Nov 2005 | Mar 2004 | refused Aug 2005 | Nov 2005 | Scottish Borders | 6.5 |
| Shaw Park Wind Farmwind farm | wind farm | 20.7 | refused on appealupdated Jun 2014 | Aug 2011 | refused Oct 2013 | Jun 2014 | Scottish Borders | 6.5 |
| Longcroft Wind Farmwind farm | wind farm | 125 | application submitted may be out of dateupdated Nov 2023 | Oct 2023 | — | Nov 2023 | Scottish Borders | 7.2 |
| Longcroft Wind Farmbattery storage | battery storage | 50 | application submitted may be out of dateupdated Nov 2023 | Oct 2023 | — | Nov 2023 | Scottish Borders | 7.2 |
| Corsbie Moor Wind Farmwind farm | wind farm | 27 | refused on appealupdated Sep 2013 | Jun 2011 | refused Sep 2012 | Sep 2013 | Scottish Borders | 7.4 |
| Ditcher Law Wind Farmwind farm | wind farm | 52.8 | approved, not builtupdated Jun 2026 | Aug 2023 | granted Feb 2026 | Jun 2026 | Scottish Borders | 7.7 |
| Ditcher Law Wind Farmbattery storage | battery storage | 30 | approved, not builtupdated Jun 2026 | Aug 2023 | granted Feb 2026 | Jun 2026 | Scottish Borders | 7.7 |
| Dun Law Extensionwind farm | wind farm | 29.8 | operationalupdated Sep 2013 | Apr 2005 | granted Jan 2006 | Sep 2013 | Scottish Borders | 8.3 |
| Longparkwind farm | wind farm | 38 | operationalupdated May 2010 | Feb 2004 | granted Aug 2005 | May 2010 | Scottish Borders | 8.3 |
| Brunta Hill Wind Farmwind farm | wind farm | 18.4 | refused on appealupdated Jun 2014 | Oct 2011 | refused Aug 2013 | Jun 2014 | Scottish Borders | 8.6 |
| Longpark Wind Farm Extensionwind farm | wind farm | 14 | application withdrawnupdated May 2017 | Apr 2014 | — | May 2017 | Scottish Borders | 8.7 |
| Toddleburnwind farm | wind farm | 27.6 | operationalupdated Oct 2010 | Sep 2004 | granted Aug 2005 | Oct 2010 | Scottish Borders | 8.7 |
Smaller schemes under 1 MW, mostly rooftop solar (1)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Nether Blainslie Sawmill, Nether Blainsliesolar farm | solar farm | 0.2 | approved, not built may be out of dateupdated Jun 2023 | Mar 2023 | granted May 2023 | Jun 2023 | Scottish Borders | 5.5 |
Distance from the average position of the TD2 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 1 | 0 | 1 | 0 | 0 | 0.2 |
| Wind farm | 13 | 1 | 1 | 3 | 6 | 178 |
| Battery storage | 2 | 1 | 1 | 0 | 0 | 80 |
MW in pipeline: pending, approved and under-construction capacity.
How Scottish Borders decides solar, wind and battery applications
| Applications | Scottish Borders | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 61 | 10,236 |
| Refused | 28 (46%) | 19% |
| Solar refused | 0 of 13 | 12% |
| Onshore wind refused | 26 of 43 | 45% |
| Battery storage refused | 2 of 5 | 16% |
| Median time from submission to decision | 51.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 11 / 6 | — |
All projects in Scottish Borders
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TD2, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.