Energy Projects Near You

Longpark (38 MW wind farm)

Longpark is a 38 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 September 2009; the record was last updated on 21 May 2010.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

38 MWwind farm
operationalstatus in REPD
21 May 2010record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
16 February 2004Application submitted
31 August 2005Planning permission granted
1 June 2009Construction started
1 September 2009Operational

Project details

Technology
wind farm
Capacity
38 MW
Status (REPD)
operational
Record last updated
21 May 2010
Operator or applicant
Wind Prospect
Planning authority
Scottish Borders
Planning application reference
04/00317/FUL
Appeal reference
P/PPA/140/251
Turbines
19
Address (REPD)
Stow
Council area (by location)
Scottish Borders
Time to decision
80 weeks
REPD reference
3605

Who decides

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Longpark Wind Farm Extensionwind farm14application withdrawn1.4
Shaw Park Wind Farmwind farm20.7refused on appeal2.3
Sell Moor Windfarmwind farm47.5refused2.4
Muircleugh Farmwind farm21refused on appeal4.0
Girthgate Wind Farmwind farm81.6appeal withdrawn5.8
Rowantree Wind Farmwind farm69refused8.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.6692, -2.8275).