Energy Projects Near You

Muircleugh Farm (21 MW wind farm)

Muircleugh Farm is a 21 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 8 December 2015; the record was last updated on 6 January 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

21 MWwind farm
refused on appealstatus in REPD
6 January 2016record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
3 October 2014Application submitted
31 March 2015Refused by the planning authority
26 June 2015Appeal lodged
8 December 2015Appeal refused

Project details

Technology
wind farm
Capacity
21 MW
Status (REPD)
refused on appeal
Record last updated
6 January 2016
Operator or applicant
Airvolution Energy
Planning authority
Scottish Borders
Planning application reference
14/01081/FUL
Appeal reference
PPA-140-2054
Turbines
7
Turbine height
110 m
Address (REPD)
Land North, West And South West Of Muircleugh Farmhouse, Lauder,
Council area (by location)
Scottish Borders
Time to decision
26 weeks
REPD reference
4103

Earlier applications for this site

ApplicationMWSubmittedOutcome
Muircleugh Farm 10/01641/FUL430 November 2010withdrawn 17 February 2011
Muircleugh Farm 13/00044/FUL1231 January 2013withdrawn 24 October 2013

Who decides

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Sell Moor Windfarmwind farm47.5refused2.6
Shaw Park Wind Farmwind farm20.7refused on appeal2.6
Girthgate Wind Farmwind farm81.6appeal withdrawn2.7
Longparkwind farm38operational4.0
Longpark Wind Farm Extensionwind farm14application withdrawn4.6
Rowantree Wind Farmwind farm69refused5.9
Corsbie Moor Wind Farmwind farm27refused on appeal8.2
Toddleburnwind farm27.6operational9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.6978, -2.7885).