Energy Projects Near You

Solar, wind and battery projects near Galashiels (TD1)

11 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TD1 (Scottish Borders): 1 is waiting for a planning decision, 4 approved but not yet running, 1 operational. The largest live scheme is Water Treatment Works, Howden Wells (1.1 MW solar farm, approved on 29 September 2023, not yet built), 9.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11projects within 10 km
1awaiting a decision
4approved, not running
1operational

Projects within 10 km of TD1

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Longparkwind farmwind farm38operationalupdated May 2010Feb 2004granted Aug 2005May 2010Scottish Borders5.2
Longpark Wind Farm Extensionwind farmwind farm14application withdrawnupdated May 2017Apr 2014—May 2017Scottish Borders6.1
Shaw Park Wind Farmwind farmwind farm20.7refused on appealupdated Jun 2014Aug 2011refused Oct 2013Jun 2014Scottish Borders7.5
Sell Moor Windfarmwind farmwind farm47.5refusedupdated Nov 2005Mar 2004refused Aug 2005Nov 2005Scottish Borders7.6
Muircleugh Farmwind farmwind farm21refused on appealupdated Jan 2016Oct 2014refused Mar 2015Jan 2016Scottish Borders8.4
Broadmeadowswind farmwind farm36refused on appealupdated Jan 2012Dec 2004refused Jun 2011Jan 2012Scottish Borders9.7
Water Treatment Works, Howden Wellssolar farmsolar farm1.1approved, not builtupdated Oct 2023Aug 2023granted Sep 2023Oct 2023Scottish Borders9.9
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Borders General Hospitalsolar farmsolar farm0.7approved, not builtupdated Jan 2025Jul 2024granted Dec 2024Jan 2025Scottish Borders5.3
Lochcarron Waverley Mill, Rodgers Roadrooftop solarrooftop solar0.2approved, not builtupdated Jul 2024May 2024granted Jul 2024Jul 2024Scottish Borders8.1
Selkirk Wastewater Treatment Works, Riverside Roadsolar farmsolar farm0.2application submittedMay 2026——Scottish Borders8.2
Nether Blainslie Sawmill, Nether Blainsliesolar farmsolar farm0.2approved, not built may be out of dateupdated Jun 2023Mar 2023granted May 2023Jun 2023Scottish Borders8.6

Distance from the average position of the TD1 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm413002.3
Rooftop solar101000.2
Wind farm600140

MW in pipeline: pending, approved and under-construction capacity.

How Scottish Borders decides solar, wind and battery applications

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

All projects in Scottish Borders

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TD1, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.