Solar, wind and battery projects near Selkirk (TD7)

6 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TD7 (Scottish Borders): 1 is waiting for a planning decision, 2 approved but not yet running, 1 operational. The largest live scheme is Water Treatment Works, Howden Wells (1.1 MW solar farm, approved on 29 September 2023, not yet built), 0.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6projects within 10 km
1awaiting a decision
2approved, not running
1operational

Projects within 10 km of TD7

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Water Treatment Works, Howden Wellssolar farmsolar farm1.1approved, not builtupdated Oct 2023Aug 2023granted Sep 2023Oct 2023Scottish Borders0.7
Broadmeadowswind farmwind farm36refused on appealupdated Jan 2012Dec 2004refused Jun 2011Jan 2012Scottish Borders5.8
Langhope Rigwind farmwind farm16operationalupdated Aug 2015Jun 2006granted Jul 2007Aug 2015Scottish Borders8.4
Barrel Law Wind Farmwind farmwind farm24refused on appealupdated Sep 2014Feb 2012refused Mar 2013Sep 2014Scottish Borders9.2
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Selkirk Wastewater Treatment Works, Riverside Roadsolar farmsolar farm0.2application submittedMay 2026——Scottish Borders2.4
Lochcarron Waverley Mill, Rodgers Roadrooftop solarrooftop solar0.2approved, not builtupdated Jul 2024May 2024granted Jul 2024Jul 2024Scottish Borders2.6

Distance from the average position of the TD7 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm211001.4
Rooftop solar101000.2
Wind farm300120

MW in pipeline: pending, approved and under-construction capacity.

How Scottish Borders decides solar, wind and battery applications

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

All projects in Scottish Borders

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.