Energy Projects Near You

Solar, wind and battery projects near Newcastleton (TD9)

8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TD9 (Scottish Borders): 3 are waiting for a planning decision, 2 approved but not yet running, 1 operational. The largest live scheme is Mid Hill Wind Farm (93.6 MW wind farm, application submitted on 27 November 2025, no decision recorded), 10.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8projects within 10 km
3awaiting a decision
2approved, not running
1operational

Projects within 10 km of TD9

Projects of 1 MW and more (6)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Birneyknowe Wind Farmwind farmwind farm60refused on appealupdated Mar 2019May 2014refused Dec 2018Mar 2019Scottish Borders3.9
Stirches Renewable Energy Park Solar Panels & Battery Energy Storagesolar farmsolar farm30application submittedupdated Aug 2025Jul 2025—Aug 2025Scottish Borders4.6
Stirches Renewable Energy Park Solar Panels & Battery Energy Storagebattery storagebattery storage30application submittedupdated Aug 2025Jul 2025—Aug 2025Scottish Borders4.6
Pines Burn Wind Farmwind farmwind farm33.6operationalupdated Apr 2026Jan 2017granted Aug 2018Apr 2026Scottish Borders5.6
Barrel Law Wind Farmwind farmwind farm24refused on appealupdated Sep 2014Feb 2012refused Mar 2013Sep 2014Scottish Borders9.8
Mid Hill Wind Farmwind farmwind farm93.6application submittedupdated Jun 2026Nov 2025—Jun 2026Scottish Borders10.0
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Burnfoot Industrial Estaterooftop solarrooftop solar0.5approved, not built may be out of dateupdated May 2022May 2022granted Jul 2022May 2022Scottish Borders4.4
Roberton Water Treatment Workssolar farmsolar farm0.2approved, not builtupdated Jul 2023Mar 2023granted Jun 2023Jul 2023Scottish Borders9.1

Distance from the average position of the TD9 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm2110030.2
Rooftop solar101000.5
Wind farm4101293.6
Battery storage1100030

MW in pipeline: pending, approved and under-construction capacity.

How Scottish Borders decides solar, wind and battery applications

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

All projects in Scottish Borders

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TD9, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.