Mid Hill Wind Farm (93.6 MW)
Mid Hill Wind Farm is a 93.6 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 27 November 2025, no decision recorded; the record was last updated on 15 June 2026. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.
Planning timeline
| Date | Stage |
|---|---|
| 27 November 2025 | Application submitted |
Project details
- Technology
- wind farm
- Capacity
- 93.6 MW
- Status (REPD)
- application submitted
- Record last updated
- 15 June 2026
- Operator or applicant
- Invenergy Services UK
- Planning authority
- Scottish Government (S36)
- Planning application reference
- ECU00005192
- Turbines
- 13
- Turbine height
- 200 m
- Address (REPD)
- N/O Harwood Farmhouse, Hawick
- Council area (by location)
- Scottish Borders
- REPD reference
- 17153
The scheme also includes 53.2 MW of battery storage, recorded separately in REPD (application submitted).
Who decides
As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Teviot Wind Farm | solar farm | 34 | application submitted | 3.8 |
| Teviot Wind Farm | wind farm | 350 | application submitted | 3.8 |
| Teviot Wind Farm | battery storage | 100 | application submitted | 3.8 |
| Barrel Law Wind Farm | wind farm | 24.5 | refused on appeal | 8.2 |
| Barrel Law Wind Farm | wind farm | 24 | refused on appeal | 9.0 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.3764, -2.9302).