Energy Projects Near You

Barrel Law Wind Farm (24.5 MW)

Barrel Law Wind Farm is a 24.5 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 23 December 2019; the record was last updated on 26 March 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

24.5 MWwind farm
refused on appealstatus in REPD
26 March 2020record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
8 September 2017Application submitted
3 September 2018Refused by the planning authority
2 November 2018Appeal lodged
23 December 2019Appeal refused

Project details

Technology
wind farm
Capacity
24.5 MW
Status (REPD)
refused on appeal
Record last updated
26 March 2020
Operator or applicant
Barrel Law Windfarm
Planning authority
Scottish Borders
Planning application reference
17/01255/FUL
Appeal reference
PPA-140-2072
Turbines
7
Turbine height
132 m
Address (REPD)
Land South West Of, Whitslade, Ashkirk, Selkirk, Borders
Council area (by location)
Scottish Borders
Time to decision
51 weeks
REPD reference
6347

Who decides

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Langhope Rigwind farm16operational2.3
Barrel Law Wind Farmwind farm24refused on appeal2.4
Mid Hill Wind Farmwind farm93.6application submitted8.2
Stirches Renewable Energy Park Solar Panels & Battery Energy Storagesolar farm30application submitted8.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.4505, -2.9312).