Energy Projects Near You

Barrel Law Wind Farm (24 MW)

Barrel Law Wind Farm is a 24 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 19 August 2014; the record was last updated on 5 September 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

24 MWwind farm
refused on appealstatus in REPD
5 September 2014record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
15 February 2012Application submitted
4 March 2013Refused by the planning authority
19 August 2014Appeal refused

Project details

Technology
wind farm
Capacity
24 MW
Status (REPD)
refused on appeal
Record last updated
5 September 2014
Operator or applicant
ABO Wind
Planning authority
Scottish Borders
Planning application reference
12/00191/FUL
Appeal reference
13/00028/REF
Turbines
8
Address (REPD)
west of the A7, roughly 3 km north of the village of Roberton and 9km north-west of Hawick in the Scottish Borders
Council area (by location)
Scottish Borders
Time to decision
55 weeks
REPD reference
4339

Who decides

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Barrel Law Wind Farmwind farm24.5refused on appeal2.4
Langhope Rigwind farm16operational3.4
Stirches Renewable Energy Park Solar Panels & Battery Energy Storagesolar farm30application submitted6.6
Mid Hill Wind Farmwind farm93.6application submitted9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.4548, -2.8946).