Energy Projects Near You

Langhope Rig (16 MW wind farm)

Langhope Rig is a 16 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 26 March 2015; the record was last updated on 24 August 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

16 MWwind farm
operationalstatus in REPD
24 August 2015record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
30 June 2006Application submitted
17 July 2007Planning permission granted
30 October 2013Construction started
26 March 2015Operational

Project details

Technology
wind farm
Capacity
16 MW
Status (REPD)
operational
Record last updated
24 August 2015
Operator or applicant
Greencoat UK Wind
Planning authority
Scottish Borders
Planning application reference
06/01236/FUL
Turbines
10
Address (REPD)
Langhope Rig, Ettrick Forest, Scottish Borders
Council area (by location)
Scottish Borders
Time to decision
55 weeks
REPD reference
4620

Who decides

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Barrel Law Wind Farmwind farm24.5refused on appeal2.3
Barrel Law Wind Farmwind farm24refused on appeal3.4
Stirches Renewable Energy Park Solar Panels & Battery Energy Storagesolar farm30application submitted9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.4707, -2.9399).