Pines Burn Wind Farm (33.6 MW)

Pines Burn Wind Farm is a 33.6 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 October 2024; the record was last updated on 30 April 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

33.6 MWwind farm
operationalstatus in REPD
30 April 2026record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
11 January 2017Application submitted
6 November 2017Refused by the planning authority
22 December 2017Appeal lodged
17 August 2018Planning permission granted
17 August 2018Appeal allowed
1 July 2022Construction started
1 October 2024Operational

Project details

Technology
wind farm
Capacity
33.6 MW
Status (REPD)
operational
Record last updated
30 April 2026
Operator or applicant
EnergieKontor UK
Planning authority
Scottish Borders
Planning application reference
17/00010/FUL
Appeal reference
PPA-140-2069
Turbines
7
Turbine height
150 m
Address (REPD)
Land South West of Lurgiescleuch, Hawick, Borders
Council area (by location)
Scottish Borders
Time to decision
83 weeks
REPD reference
6147

Who decides

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Birneyknowe Wind Farmwind farm60refused on appeal4.8
Chesters - Millmoor Rig Wind Farm & Battery Energy Storagewind farm78application submitted9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.3537, -2.7303).