Birneyknowe Wind Farm (60 MW)

Birneyknowe Wind Farm is a 60 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 21 December 2018; the record was last updated on 26 March 2019. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

60 MWwind farm
refused on appealstatus in REPD
26 March 2019record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
14 May 2014Application submitted
12 May 2017Appeal lodged
21 December 2018Refused by the planning authority
21 December 2018Appeal refused

Project details

Technology
wind farm
Capacity
60 MW
Status (REPD)
refused on appeal
Record last updated
26 March 2019
Operator or applicant
Banks Renewables
Planning authority
Scottish Government (S36)
Planning application reference
EC00002092
Appeal reference
WIN-140-7
Turbines
15
Address (REPD)
Hawick, Borders
Council area (by location)
Scottish Borders
Time to decision
240 weeks
REPD reference
4342

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Pines Burn Wind Farmwind farm33.6operational4.8
Stirches Renewable Energy Park Solar Panels & Battery Energy Storagesolar farm30application submitted6.8
Cummings Hill Wind Farmwind farm21application withdrawn8.8
Chesters - Millmoor Rig Wind Farm & Battery Energy Storagewind farm78application submitted8.9
Dunion Hill Wind Farmwind farm18.4refused9.0
Highlee Hill Wind Farmwind farm44.9application withdrawn9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.3959, -2.715).