Energy Projects Near You

Chesters - Millmoor Rig Wind Farm & Battery Energy Storage (78 MW)

Chesters - Millmoor Rig Wind Farm & Battery Energy Storage is a 78 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 28 November 2022, no decision recorded; the record was last updated on 12 December 2022. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

78 MWwind farm
application submittedmay be out of datestatus in REPD
12 December 2022record last updated
Scottish Borderscouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
28 November 2022Application submitted

Project details

Technology
wind farm
Capacity
78 MW
Status (REPD)
application submitted
Record last updated
12 December 2022
Operator or applicant
ESB Asset Development UK Ltd
Planning authority
Scottish Government (S36)
Planning application reference
ECU00003426
Turbines
13
Turbine height
230 m
Address (REPD)
SW/O Chesters, Harwick
Council area (by location)
Scottish Borders
REPD reference
10715

The scheme also includes 20 MW of battery storage, recorded separately in REPD (application submitted).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Cummings Hill Wind Farmwind farm21application withdrawn3.7
Birneyknowe Wind Farmwind farm60refused on appeal8.9
Dunion Hill Wind Farmwind farm18.4refused9.0
Pines Burn Wind Farmwind farm33.6operational9.5
Highlee Hill Wind Farmwind farm44.9application withdrawn9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.3703, -2.5821).