Sell Moor Windfarm (47.5 MW)

Sell Moor Windfarm is a 47.5 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 31 August 2005; the record was last updated on 8 November 2005.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

47.5 MWwind farm
refusedstatus in REPD
8 November 2005record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
1 March 2004Application submitted
31 August 2005Refused by the planning authority

Project details

Technology
wind farm
Capacity
47.5 MW
Status (REPD)
refused
Record last updated
8 November 2005
Operator or applicant
RDC Scotland Ltd
Planning authority
Scottish Borders
Planning application reference
04/00350/FUL
Address (REPD)
Lauder
Council area (by location)
Scottish Borders
Time to decision
78 weeks
REPD reference
3215

Who decides

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Shaw Park Wind Farmwind farm20.7refused on appeal0.1
Longpark Wind Farm Extensionwind farm14application withdrawn2.3
Longparkwind farm38operational2.4
Muircleugh Farmwind farm21refused on appeal2.6
Girthgate Wind Farmwind farm81.6appeal withdrawn3.5
Rowantree Wind Farmwind farm69refused5.6
Toddleburnwind farm27.6operational9.2
Wind Farm at Greystone Knowe Wind Farmwind farm75application submitted10.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.6907, -2.8279).