Wind Farm at Greystone Knowe Wind Farm (75 MW)

Wind Farm at Greystone Knowe Wind Farm is a 75 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 27 October 2021, no decision recorded; the record was last updated on 18 November 2021. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

75 MWwind farm
application submittedmay be out of datestatus in REPD
18 November 2021record last updated
Scottish Borderscouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
27 October 2021Application submitted

Project details

Technology
wind farm
Capacity
75 MW
Status (REPD)
application submitted
Record last updated
18 November 2021
Operator or applicant
Coriolis Energy Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00003341
Turbines
14
Turbine height
180 m
Address (REPD)
Greystone Knowe Wind Farm, Sw/O Brockhouse Farmhouse, Fountainhall, Galashiels
Council area (by location)
Scottish Borders
Name in REPD
Greystone Knowe Wind Farm - Wind Farm
REPD reference
9953

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Wull Muir Wind Farmwind farm36refused3.5
Carcant Windfarmwind farm6operational4.7
Falahillwind farm6.7refused6.1
Toddleburnwind farm27.6operational6.9
Bowbeat Emly Bank / Rough Sidewind farm31.2operational7.0
Penicuik, Moorfoot Hills - Torfichen Wind Farmwind farm108application submitted7.5
Rowantree Wind Farmwind farm69refused7.7
Gilston Hill Wind Farmwind farm21refused on appeal9.4
Scawd Law Wind Farmwind farm48application submitted9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7333, -2.9682).