Falahill (6.7 MW wind farm)

Falahill is a 6.7 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 8 May 2006; the record was last updated on 5 May 2006.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.7 MWwind farm
refusedstatus in REPD
5 May 2006record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
10 December 2004Application submitted
8 May 2006Refused by the planning authority

Project details

Technology
wind farm
Capacity
6.7 MW
Status (REPD)
refused
Record last updated
5 May 2006
Operator or applicant
E.ON UK
Planning authority
Scottish Borders
Planning application reference
04/02420/FUL
Address (REPD)
Falahill Farm Falahill Heriot Midlothian
Council area (by location)
Scottish Borders
Time to decision
73 weeks
REPD reference
3506

Who decides

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Wull Muir Wind Farmwind farm36refused2.7
Carcant Windfarmwind farm6operational3.9
Gilston Hill Wind Farmwind farm21refused on appeal5.3
Penicuik, Moorfoot Hills - Torfichen Wind Farmwind farm108application submitted5.5
Wind Farm at Greystone Knowe Wind Farmwind farm75application submitted6.1
Toddleburnwind farm27.6operational6.3
Gilston Wind Farm (Lothian)wind farm18.5refused on appeal6.3
Gilston Wind Farm (Borders)wind farm14.4refused on appeal6.3
Dun Law Extensionwind farm29.8operational8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7884, -2.9714).