Energy Projects Near You

Solar, wind and battery projects near Pathhead (EH37)

16 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of EH37 (Midlothian): 7 approved but not yet running, 4 operational. The largest live scheme is Smeaton Battery Energy Storage System (228 MW battery storage, approved on 29 August 2024, not yet built), 7.5 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Forthwind (20 MW, approved, not built), 32.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

16projects within 10 km
0awaiting a decision
7approved, not running
4operational

Projects within 10 km of EH37

Projects of 1 MW and more (11)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Gilston Wind Farm (Lothian)wind farmwind farm18.5refused on appealupdated Sep 2013Dec 2011refused Dec 2012Sep 2013Midlothian5.7
Gilston Wind Farm (Borders)wind farmwind farm14.4refused on appealupdated Sep 2013Dec 2011refused Dec 2012Sep 2013Midlothian5.7
Salters Battery Energy Storage Systembattery storagebattery storage200approved, not builtupdated Jul 2025Aug 2024granted May 2025Jul 2025Midlothian6.9
Gilston Hill Wind Farmwind farmwind farm21refused on appealupdated Apr 2020Feb 2017refused Feb 2017Apr 2020Midlothian7.4
Smeaton Battery Energy Storage Systembattery storagebattery storage228approved, not builtupdated Oct 2024Mar 2023granted Aug 2024Oct 2024East Lothian7.5
Pogbie Wind Farm 2wind farmwind farm4.8operationalupdated Dec 2019Aug 2015granted May 2016Dec 2019East Lothian7.7
Falahillwind farmwind farm6.7refusedupdated May 2006Dec 2004refused May 2006May 2006Scottish Borders8.1
Pogbie Wind Farm 1wind farmwind farm5.1operationalupdated Apr 2019Sep 2008granted Sep 2009Apr 2019East Lothian9.1
Dun Lawwind farmwind farm17.2operationalupdated Sep 2013May 1996granted Jul 1997Sep 2013Midlothian9.4
Dolphingstone Farmbattery storagebattery storage63approved, not builtupdated Oct 2025Nov 2023granted Jul 2025Oct 2025East Lothian9.4
Keith Hillwind farmwind farm4.5operationalupdated Sep 2018Nov 2010granted Apr 2011Sep 2018East Lothian9.7
Smaller schemes under 1 MW, mostly rooftop solar (5)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Meadow Stores, Ormistonsolar farmsolar farm0.2approved, not builtupdated Nov 2024Sep 2024granted Nov 2024Nov 2024East Lothian6.8
Butlerfield Industrial Estaterooftop solarrooftop solar0.4approved, not built may be out of dateupdated Jan 2023Nov 2022granted Jan 2023Jan 2023Midlothian6.9
Edinburgh College, Dalhousie Roadrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Jul 2023May 2023granted Jul 2023Jul 2023Midlothian7.8
Wull Muir Wind Farmbattery storagebattery storage—refusedupdated Aug 2024Dec 2022refused Jul 2024Aug 2024Scottish Borders9.7
Old Dalkeith Road, Danderhallrooftop solarrooftop solar0.1approved, not built may be out of dateupdated Mar 2022Mar 2022granted Apr 2022Mar 2022Midlothian10.0

Distance from the average position of the EH37 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm101000.2
Rooftop solar303000.7
Wind farm800440
Battery storage40301491

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Forthwind20approved, not builtupdated Aug 202332.8
Levenmouth demonstration turbine (Fife Energy Park)7operationalupdated Nov 201833.3

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Midlothian decides solar, wind and battery applications

ApplicationsMidlothianUK
Decided applications (solar, wind, battery)1110,236
Refused4 (36%)19%
Solar refused0 of 712%
Onshore wind refused4 of 445%
Median time from submission to decision45.4 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

All projects in Midlothian

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near EH37, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.