Gilston Wind Farm (Borders) (14.4 MW)

Gilston Wind Farm (Borders) is a 14.4 MW wind farm project in Midlothian, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 29 August 2013; the record was last updated on 13 September 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14.4 MWwind farm
refused on appealstatus in REPD
13 September 2013record last updated
Midlothiancouncil area

Planning timeline

DateStage
21 December 2011Application submitted
10 December 2012Refused by the planning authority
29 August 2013Appeal refused

Project details

Technology
wind farm
Capacity
14.4 MW
Status (REPD)
refused on appeal
Record last updated
13 September 2013
Operator or applicant
Ridgewind
Planning authority
Midlothian
Planning application reference
11/01680/FUL
Appeal reference
13/00010/REF
Turbines
7
Address (REPD)
south of the village of Fala and just to the west of the existing Dun Law wind farm
Council area (by location)
Midlothian
Time to decision
51 weeks
REPD reference
3909

Who decides

ApplicationsMidlothianUK
Decided applications (solar, wind, battery)1110,236
Refused4 (36%)19%
Solar refused0 of 712%
Onshore wind refused4 of 445%
Median time from submission to decision45.4 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Gilston Wind Farm (Lothian)wind farm18.5refused on appeal<0.1
Gilston Hill Wind Farmwind farm21refused on appeal2.1
Dun Lawwind farm17.2operational3.7
Pogbie Wind Farm 1wind farm5.1operational3.9
Dun Law Extensionwind farm29.8operational5.4
Falahillwind farm6.7refused6.3
Toddleburnwind farm27.6operational6.4
Ditcher Law Wind Farmwind farm52.8approved, not built6.6
Wull Muir Wind Farmwind farm36refused8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8254, -2.8949).