Dun Law Extension (29.8 MW wind farm)

Dun Law Extension is a 29.8 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 20 September 2009; the record was last updated on 12 September 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

29.8 MWwind farm
operationalstatus in REPD
12 September 2013record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
27 April 2005Application submitted
16 January 2006Planning permission granted
1 May 2009Construction started
20 September 2009Operational

Project details

Technology
wind farm
Capacity
29.8 MW
Status (REPD)
operational
Record last updated
12 September 2013
Operator or applicant
Renewable Energy Systems (RES)
Planning authority
Scottish Borders
Planning application reference
not recorded
Turbines
35
Address (REPD)
Dun Law (between Fala and Carfraemill 20 miles S-E of Edinburgh
Council area (by location)
Scottish Borders
Time to decision
38 weeks
REPD reference
3579

Who decides

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Dun Lawwind farm17.2operational2.2
Ditcher Law Wind Farmwind farm52.8approved, not built2.6
Toddleburnwind farm27.6operational3.0
Gilston Hill Wind Farmwind farm21refused on appeal3.8
Pogbie Wind Farm 1wind farm5.1operational3.9
Rowantree Wind Farmwind farm69refused5.2
Gilston Wind Farm (Lothian)wind farm18.5refused on appeal5.4
Gilston Wind Farm (Borders)wind farm14.4refused on appeal5.4
Longcroft Wind Farmwind farm125application submitted7.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7868, -2.8423).