Energy Projects Near You

Renewable energy projects in Midlothian

18 solar, wind or battery projects of 150 kW or more are located in Midlothian (REPD, July 2026 extract): 4 pending, 8 approved but not running, 1 operational and 5 refused. The council refused 4 of 11 decided applications (36%; UK 19%), with a median 45 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18projects in the council area
4awaiting a decision
8approved, not running
36%of decisions refused

How Midlothian decides

ApplicationsMidlothianUK
Decided applications (solar, wind, battery)1110,236
Refused4 (36%)19%
Solar refused0 of 712%
Onshore wind refused4 of 445%
Median time from submission to decision45.4 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Projects in Midlothian

Projects of 1 MW and more (10)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Salters Battery Energy Storage Systembattery storagebattery storage200approved, not builtupdated Jul 2025Aug 2024granted May 2025Jul 2025
Penicuik, Moorfoot Hills - Torfichen Wind Farmwind farmwind farm108application submitted may be out of dateupdated Feb 2023Nov 2023—Feb 2023
Penicuik, Moorfoot Hills - Torfichen Wind Farmbattery storagebattery storage50application submitted may be out of dateupdated Mar 2023Nov 2023—Mar 2023
Auchencorth Mosswind farmwind farm45refusedupdated Oct 2009Jan 2006refused Feb 2008Oct 2009
Gilston Hill Wind Farmwind farmwind farm21refused on appealupdated Apr 2020Feb 2017refused Feb 2017Apr 2020
Mount Lothian Wind Farmwind farmwind farm20.7refused on appealupdated Nov 2015Jan 2014refused Nov 2015Nov 2015
Gilston Wind Farm (Lothian)wind farmwind farm18.5refused on appealupdated Sep 2013Dec 2011refused Dec 2012Sep 2013
Dun Lawwind farmwind farm17.2operationalupdated Sep 2013May 1996granted Jul 1997Sep 2013
Gilston Wind Farm (Borders)wind farmwind farm14.4refused on appealupdated Sep 2013Dec 2011refused Dec 2012Sep 2013
Easter Bushsolar farmsolar farm3under constructionupdated Sep 2020Jan 2019granted Oct 2021Sep 2020
Smaller schemes under 1 MW, mostly rooftop solar (8)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Sainsburys Supermarket, Straiton Mainsrooftop solarrooftop solar0.6application submitted may be out of dateupdated Aug 2023Aug 2023—Aug 2023
Butlerfield Industrial Estaterooftop solarrooftop solar0.4approved, not built may be out of dateupdated Jan 2023Nov 2022granted Jan 2023Jan 2023
Rullion Roadsolar farmsolar farm0.3approved, not builtupdated May 2025Feb 2025granted Apr 2025May 2025
Silverburn Water Tank, Hopelands Roadsolar farmsolar farm0.2approved, not builtupdated Sep 2023Oct 2022granted Sep 2023Sep 2023
Hawthornden Castlesolar farmsolar farm0.2approved, not builtupdated Jun 2024Oct 2023granted Apr 2024Jun 2024
Edinburgh College, Dalhousie Roadrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Jul 2023May 2023granted Jul 2023Jul 2023
Old Dalkeith Road, Danderhallrooftop solarrooftop solar0.1approved, not built may be out of dateupdated Mar 2022Mar 2022granted Apr 2022Mar 2022
James Hamilton Way Solar Farmsolar farmsolar farm—application submitted may be out of dateupdated Mar 2022Feb 2022—Mar 2022

Postcode districts in Midlothian

DistrictProjects within 10 kmPendingApprovedOperational
EH18193141
EH19153110
EH20224151
EH22133100
EH2319571
EH24185100
EH25204130
EH2611440
EH3716074

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Midlothian by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.