Auchencorth Moss (45 MW wind farm)

Auchencorth Moss is a 45 MW wind farm project in Midlothian, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 12 February 2008; the record was last updated on 5 October 2009.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

45 MWwind farm
refusedstatus in REPD
5 October 2009record last updated
Midlothiancouncil area

Planning timeline

DateStage
27 January 2006Application submitted
12 February 2008Refused by the planning authority

Project details

Technology
wind farm
Capacity
45 MW
Status (REPD)
refused
Record last updated
5 October 2009
Operator or applicant
E.ON UK
Planning authority
Midlothian
Planning application reference
06/00067/FUL
Turbines
18
Address (REPD)
Auchencorth Moss Penicuik Midlothian
Council area (by location)
Midlothian
Time to decision
107 weeks
REPD reference
3268

Who decides

ApplicationsMidlothianUK
Decided applications (solar, wind, battery)1110,236
Refused4 (36%)19%
Solar refused0 of 712%
Onshore wind refused4 of 445%
Median time from submission to decision45.4 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Spurlens Rig Wind Clusterwind farm12refused4.6
Mount Lothian Wind Farmwind farm20.7refused on appeal5.8
Kilrubie Wind Farmwind farm21appeal withdrawn8.6
Cloich Forest Wind Farmwind farm63application submitted8.8
Hag Lawwind farm20refused on appeal9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7977, -3.2604).