Spurlens Rig Wind Cluster (12 MW)

Spurlens Rig Wind Cluster is a 12 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 30 November 2011; the record was last updated on 27 January 2012.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWwind farm
refusedstatus in REPD
27 January 2012record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
7 December 2010Application submitted
30 November 2011Refused by the planning authority

Project details

Technology
wind farm
Capacity
12 MW
Status (REPD)
refused
Record last updated
27 January 2012
Operator or applicant
Lomond Energy
Planning authority
Scottish Borders
Planning application reference
10/01669/FUL
Turbines
6
Address (REPD)
near Leadburn, Scottish Borders
Council area (by location)
Scottish Borders
Time to decision
51 weeks
REPD reference
2765

Who decides

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Mount Lothian Wind Farmwind farm20.7refused on appeal2.8
Auchencorth Mosswind farm45refused4.6
Kilrubie Wind Farmwind farm21appeal withdrawn6.3
Cloich Forest Wind Farmwind farm63application submitted7.2
Hag Lawwind farm20refused on appeal8.3
Penicuik, Moorfoot Hills - Torfichen Wind Farmwind farm108application submitted9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7736, -3.2011).