Energy Projects Near You

Solar, wind and battery projects near Penicuik (EH26)

11 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of EH26 (Midlothian): 4 are waiting for a planning decision, 4 approved but not yet running. The largest live scheme is Riccarton Mains Road (150 MW battery storage, application submitted on 26 March 2025, no decision recorded), 9.2 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Forthwind (20 MW, approved, not built), 38.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11projects within 10 km
4awaiting a decision
4approved, not running
0operational

Projects within 10 km of EH26

Projects of 1 MW and more (6)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Easter Bushsolar farmsolar farm3under constructionupdated Sep 2020Jan 2019granted Oct 2021Sep 2020Midlothian4.2
Auchencorth Mosswind farmwind farm45refusedupdated Oct 2009Jan 2006refused Feb 2008Oct 2009Midlothian4.7
Mount Lothian Wind Farmwind farmwind farm20.7refused on appealupdated Nov 2015Jan 2014refused Nov 2015Nov 2015Midlothian5.9
Spurlens Rig Wind Clusterwind farmwind farm12refusedupdated Jan 2012Dec 2010refused Nov 2011Jan 2012Scottish Borders6.9
Existing Kaimes Substation, Old Burdiehouse Roadbattery storagebattery storage49.9application submitted may be out of dateupdated Apr 2024Mar 2024—Apr 2024City of Edinburgh7.8
Riccarton Mains Roadbattery storagebattery storage150application submittedupdated Oct 2025Mar 2025—Oct 2025City of Edinburgh9.2
Smaller schemes under 1 MW, mostly rooftop solar (5)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Rullion Roadsolar farmsolar farm0.3approved, not builtupdated May 2025Feb 2025granted Apr 2025May 2025Midlothian0.9
Silverburn Water Tank, Hopelands Roadsolar farmsolar farm0.2approved, not builtupdated Sep 2023Oct 2022granted Sep 2023Sep 2023Midlothian2.9
James Hamilton Way Solar Farmsolar farmsolar farm—application submitted may be out of dateupdated Mar 2022Feb 2022—Mar 2022Midlothian3.4
Hawthornden Castlesolar farmsolar farm0.2approved, not builtupdated Jun 2024Oct 2023granted Apr 2024Jun 2024Midlothian5.9
Sainsburys Supermarket, Straiton Mainsrooftop solarrooftop solar0.6application submitted may be out of dateupdated Aug 2023Aug 2023—Aug 2023Midlothian6.8

Distance from the average position of the EH26 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm514003.7
Rooftop solar110000.6
Wind farm300030
Battery storage22000200

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Forthwind20approved, not builtupdated Aug 202338.4
Levenmouth demonstration turbine (Fife Energy Park)7operationalupdated Nov 201839.9

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Midlothian decides solar, wind and battery applications

ApplicationsMidlothianUK
Decided applications (solar, wind, battery)1110,236
Refused4 (36%)19%
Solar refused0 of 712%
Onshore wind refused4 of 445%
Median time from submission to decision45.4 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

All projects in Midlothian

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near EH26, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.