Mount Lothian Wind Farm (20.7 MW)

Mount Lothian Wind Farm is a 20.7 MW wind farm project in Midlothian, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 26 November 2015; the record was last updated on 30 November 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20.7 MWwind farm
refused on appealstatus in REPD
30 November 2015record last updated
Midlothiancouncil area

Planning timeline

DateStage
28 January 2014Application submitted
26 August 2014Appeal lodged
26 November 2015Refused by the planning authority
26 November 2015Appeal refused

Project details

Technology
wind farm
Capacity
20.7 MW
Status (REPD)
refused on appeal
Record last updated
30 November 2015
Operator or applicant
Wind Prospect Developments
Planning authority
Midlothian
Planning application reference
14/00044/DPP
Appeal reference
PPA-290-2025
Turbines
9
Address (REPD)
Mount Lothian Moss Penicuik
Council area (by location)
Midlothian
Time to decision
95 weeks
REPD reference
4401

Earlier applications for this site

ApplicationMWSubmittedOutcome
Mount Lothian Wind Farm 13/00063/DPP20.730 January 2013withdrawn 17 May 2013

Who decides

ApplicationsMidlothianUK
Decided applications (solar, wind, battery)1110,236
Refused4 (36%)19%
Solar refused0 of 712%
Onshore wind refused4 of 445%
Median time from submission to decision45.4 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Spurlens Rig Wind Clusterwind farm12refused2.8
Auchencorth Mosswind farm45refused5.8
Penicuik, Moorfoot Hills - Torfichen Wind Farmwind farm108application submitted7.1
Kilrubie Wind Farmwind farm21appeal withdrawn9.0
Carcant Windfarmwind farm6operational9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7908, -3.1683).